    We want to thank our residents at all 5 locations for their patience while this upgrade is in process. We truly feel that the overall benefit will be invaluable. Please continue to check our message board daily for updates on the tentative schedule. This schedule should stay on track, but we do want to leave some room for possible delays. All information will be posted as we receive it.

    UPDATE: Friday, September
    Due to the weather, we suspended all work for today.
    Energy Masters will be back on Monday, September 19th to complete the following:

    SPYGLASS
    2600,2606,2601,2607,2615,2621,2627
    2624 IS COMPLETE
    RIVER REACH
    Bldgs 6, 2

    PARK PLACE, SOUTH POINTE, and CHERRY HILLS ARE COMPLETE

    UPDATE: Thursday, September 15th

    RIVER REACH
    Bldg 10 – air test on Friday (16th)
    Bldg 6 – complete on Friday (16th)
    Bldg 2 – start and complete Friday (16th)

    SPYGLASS
    2600, 2606, 2601 – blow insulation on Friday (16th)
    2607, 2615, 2621, 2624, 2627 – start work on Friday (16th)
    sending additional crews to try to finish by end of day

    157 PARK PLACE
    ** ALL WORK COMPLETE **

    CHERRY HILLS
    ** ALL WORK COMPLETE **

    SOUTH POINTE
    ** ALL WORK COMPLETE **

    UPDATE: September 13th & September 14th

    157 PARK PLACE (ROTTINGHAM COURT)
    1-15, 17-31, 4-18 will finish on Wednesday (Sept 14)
    33-47, 20-34, 36-50 will start on Wednesday (Sept 14)
    97-111, 81-95, 84-98 – all work complete
    65-79- all work complete as of 9/14
    33-47, 20-34, 36-50; will start work on Thursday (Sept 15)

    SPYGLASS
    2600, 2606 will finish on Wednesday (Sept 14), will post test Thursday (Sept 15)
    2601 will start on Wednesday (Sept 14)
    2607, 2615 will start on Thursday (Sept 15)

    CHERRY HILLS TOWN HOMES
    1130 – all work complete
    809 – will complete Wednesday (Sept 14) and post-test on Thursday (Sept 15)
    17 – will begin work on Wednesday (Sept 14)- Completion of this building Thursday (Sept 15)
    25- Work Begins Thursday (September 15)

    SOUTH POINTE
    201, 203, 301 all work complete
    303 – will complete Wednesday (Sept 14)
    305, 205 – work completed Thursday (September 15) mid-day

    RIVER REACH
    1, 17 – all work complete
    5, 9 – will post test on Wednesday (Sept 14)
    13 – will complete work on Wednesday (Sept 14)
    14- work completed Wednesday (Sept 14)
    10- partial completed Wednesday (Sept 14)- finishing Thursday (Sept 15)- Post Testing Thursday 9/15
    6- work begins Thursday (September 15)
    2- work begins on Friday (September 16)

    ***PLEASE NOTE: THIS INFORMATION WILL BE UPDATED AS WE RECEIVE COMPLETION INFORMATION FROM THE CREWS ON-SITE. DETAILS WILL BE UPDATED AT LEAST ONCE A DAY (IN THE AFTERNOON). CONCERNS CAN BE EMAILED TO OUR OFFICE @ OFFICE@CHERRY-HILLS.NET.